A Performance Forecasting Model for Optimizing CDF-Funded Construction Projects in the Copperbelt Province, Zambia

Authors

DOI:

https://doi.org/10.25034/ijcua.2025.v9n1-15

Keywords:

Constituency Development Fund (CDF), Adaptive Neuro-Fuzzy Inference Systems (ANFIS), Analytical Hierarchy Process (AHP), Performance Forecasting, Project Management

Abstract

The Constituency Development Fund (CDF) has become a key mechanism for delivering small-scale urban infrastructure in Zambia. However, persistent challenges such as project delays, cost overruns, and quality deficiencies undermine the effectiveness of these interventions. This study addresses a critical gap in the literature and practice by developing a novel performance forecasting model tailored to the unique governance and technical context of CDF-funded projects. The model integrates Adaptive Neuro-Fuzzy Inference Systems (ANFIS) with the Analytic Hierarchy Process (AHP) to forecast performance across five key indicators: cost-effectiveness, schedule adherence, quality compliance, safety performance, and client satisfaction. Using stakeholder data from 196 respondents and historical project records, the model was trained and validated using MATLAB. It achieved strong predictive accuracy, with a coefficient of determination (R²) of 0.92 and a root mean square error (RMSE) of 0.09. These results demonstrate the model’s utility as a decision-support tool for local authorities and urban planners, enabling early detection of underperformance and facilitating proactive interventions. The model contributes to performance-based planning by providing a data-driven, stakeholder-informed forecasting framework that is adaptable to resource-constrained environments. Its application can enhance transparency, optimize resource use, and support inclusive urban development in rapidly growing municipalities.

Downloads

Download data is not yet available.

Author Biographies

  • Peter Kakoma, Department of Civil and Environmental Engineering, School of Engineering, University of Zambia, Zambia

     

     

     

     

  • Moffat Tembo, Department of Civil and Environmental Engineering, School of Engineering, University of Zambia, Zambia

     

     

  • Erastus Misheng’u Mwanaumo, Built Environment and Information Technology, Faculty of Engineering, Walter Sisulu University, South Africa

     

     

     

References

Adams, E. A., & Boateng, G. O. (2018). Are urban informal communities capable of co-production? The influence of community–public partnerships on water access in Lilongwe, Malawi. Environment and Urbanization, 30(2), 461-480. https://doi.org/10.1177/0956247818792059 DOI: https://doi.org/10.1177/0956247818792059

Akamani, K., & Hall, T. E. (2015). Determinants of the process and outcomes of household participation in collaborative forest management in Ghana: A quantitative test of a community resilience model. Journal of environmental management, 147, 1-11. https://doi.org/10.1016/j.jenvman.2014.09.007 DOI: https://doi.org/10.1016/j.jenvman.2014.09.007

Alshibani, A., Hafez, B. E., Hassanain, M. A., Mohammed, A., Al-Osta, M., & Bahraq, A. (2024). Fuzzy Logic-Based Method for Forecasting Project Final Cost. Buildings, 14(12), 3738. https://doi.org/10.3390/buildings14123738 DOI: https://doi.org/10.3390/buildings14123738

Ansari, R., Khalilzadeh, M., Taherkhani, R., Antucheviciene, J., Migilinskas, D., & Moradi, S. (2022). Performance prediction of construction projects based on the causes of claims: A system dynamics approach. Sustainability, 14(7), 4138. https://doi.org/10.3390/su14074138 DOI: https://doi.org/10.3390/su14074138

Arora, M., Verma, S., Kavita, Wozniak, M., Shafi, J., & Ijaz, M. F. (2022). An efficient ANFIS-EEBAT approach to estimate effort of Scrum projects. Scientific Reports, 12(1), 7974. https://doi.org/10.1038/s41598-022-11565-2 DOI: https://doi.org/10.1038/s41598-022-11565-2

Bateganya, N. L., Beardsley, R., Lebu, S., Atim, J., Lilian, K. S., Lahai, F., Madeira, M. M., Mulenga, O. C., & Manga, M. (2023). Shifting from traditional infrastructure planning to a collaborative approach: lessons from the Freetown sanitation master plan. Journal of Water, Sanitation and Hygiene for Development, 13(12), 974–985. https://doi.org/10.2166/washdev.2023.171 DOI: https://doi.org/10.2166/washdev.2023.171

Creswell, J. W., & Clark, V. L. P. (2017). Designing and conducting mixed methods research (3rd ed.). SAGE Publications. 520pp. ISBN: 978-1483346984

Diep, L., Mulligan, J., Oloo, M. A., Guthmann, L., Raido, M., & Ndezi, T. (2022). Co building trust in urban nature: Learning from participatory design and construction of nature based solutions in informal settlements in East Africa. Frontiers in Sustainable Cities, 4, 927723. https://doi.org/10.3389/frsc.2022.927723 DOI: https://doi.org/10.3389/frsc.2022.927723

Hapompwe, C. C., Tembo, M. N., & Zyambo, E. (2020). An Assessment of the impact of constituency development fund on rural development in education and health sectors in Rufunsa Constituency, Zambia. International Journal of Scientific and Research Publications (IJSRP), 10(08), 104-110. https://doi.org/10.29322/IJSRP.10.08.2020.p104110 DOI: https://doi.org/10.29322/IJSRP.10.06.2020.p10245

Healey, P. (2017). Making better places: The planning project in the twenty-first century. Bloomsbury Publishing.

Jang, J.-S. R. (1993). ANFIS: Adaptive-network-based fuzzy inference system. IEEE Transactions on Systems, Man, and Cybernetics, 23(3), 665–685. https://doi.org/10.1109/21.256541 DOI: https://doi.org/10.1109/21.256541

Jolliffe, I. T., & Cadima, J. (2016). Principal component analysis: a review and recent developments. Philosophical transactions of the royal society A: Mathematical, Physical and Engineering Sciences, 374(2065), 20150202. https://doi.org/10.1098/rsta.2015.0202 DOI: https://doi.org/10.1098/rsta.2015.0202

Kabwe, C., Innocent, M., & Muleya, F. (2023). Assessment of Infrastructure Development Approach in Newly Created Districts in Zambia: Case Study. CSID Journal of Infrastructure Development, 6(2), 10. https://doi.org/10.7454/jid.v6.i2.1128 DOI: https://doi.org/10.7454/jid.v6.i2.1128

Mamokhere, J., & Meyer, D. F. (2022). Comprehending stakeholders’ involvement in the integrated development planning process as a tool for improved community participation. EUREKA: Social and Humanities, (4), 18-32. https://doi.org/10.21303/2504-5571.2022.002426 DOI: https://doi.org/10.21303/2504-5571.2022.002426

Marakas, G. M. (2003). Decision support systems in the 21st century (2nd ed.). Prentice Hall.

Mavi, N. K., Brown, K., Fulford, R., & Goh, M. (2024). Forecasting project success in the construction industry using adaptive neuro-fuzzy inference system. International Journal of Construction Management, 24(14), 1550–1568. https://doi.org/10.1080/15623599.2023.2266676 DOI: https://doi.org/10.1080/15623599.2023.2266676

Medayese, S., Magidimisha-Chipungu, H. H., Chipungu, L., & Popoola, A. A. (2021). Situating citizens’ participation in inclusive infrastructure development. Urban Inclusivity in Southern Africa, 395-416. https://doi.org/10.1007/978-3-030-81511-0_18 DOI: https://doi.org/10.1007/978-3-030-81511-0_18

Mitullah, W. V. (2017). Non-motorized transport integration into urban transport planning in Africa. M. J. W. A. Vanderschuren, & M. Khayesi (Eds.). New York: Routledge. DOI: https://doi.org/10.4324/9781315598451

Musonda, I., Zulu, S. L., Zulu, E., & Kavishe, N. (2025). Understanding clients’ role in community stakeholder participation and influence on infrastructure sustainability—a stakeholder theory lens. International Journal of Construction Management, 25(4), 419–427. https://doi.org/10.1080/15623599.2024.2331862 DOI: https://doi.org/10.1080/15623599.2024.2331862

Naji, K. K., Gunduz, M., & Naser, A. F. (2022). An adaptive neurofuzzy inference system for the assessment of change order management performance in construction. Journal of Management in Engineering, 38(2), 04021098. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001017 DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0001017

Ntwana, B. & Naidoo, V. (2024). The Impact of Public Participation Through Invited and Invented Spaces on Water Supply in Urban Informal Settlements. Urban Forum, 35(4), 571–601. https://doi.org/10.1007/s12132-024-09523-4 DOI: https://doi.org/10.1007/s12132-024-09523-4

Nyamori, R. O. (2009). Making development accountable: A critical analysis of the systems of accounting and accountability for the Constituency Development Fund in Kenya. Journal of Accounting & Organizational Change, 197–227. https://doi.org/10.1108/18325910910963436 DOI: https://doi.org/10.1108/18325910910963436

Saad, S., Alaloul, W. S., Ammad, S., Altaf, M., & Qureshi, A. H. (2022). Identification of critical success factors for the adoption of Industrialized Building System (IBS) in Malaysian construction industry. Ain Shams Engineering Journal, 13(2), 101547. https://doi.org/10.1016/j.asej.2021.06.031 DOI: https://doi.org/10.1016/j.asej.2021.06.031

Saaty, T. L. (2008). Decision making with the analytic hierarchy process. International Journal of Services Sciences, 1(1), 83–98. https://doi.org/10.1504/IJSSCI.2008.017590 DOI: https://doi.org/10.1504/IJSSCI.2008.017590

Shigute, Z. (2022). Community participation and the quality of rural infrastructure in Ethiopia. Journal of African Economies, 31(4), 355-383. https://doi.org/10.1093/jae/ejab017 DOI: https://doi.org/10.1093/jae/ejab017

Sikombe, S., & Phiri, M. A. (2021). Institutional factors influencing institutionalised supplier development initiatives in the construction industry in Zambia. Cogent Business & Management, 8(1), 1935184. https://doi.org/10.1080/23311975.2021.1935184 DOI: https://doi.org/10.1080/23311975.2021.1935184

Veta, O. D. (2025). Exploring participatory approach to community development projects in Africa: Toward an empowerment-participatory approach for sustainable development. Journal of Social Work, 25(3), 301-317. https://doi.org/10.1177/14680173241283396 DOI: https://doi.org/10.1177/14680173241283396

Downloads

Published

2025-06-20

How to Cite

Kakoma, P., Nyimbili, P. H., Tembo, M., & Mwanaumo, E. M. (2025). A Performance Forecasting Model for Optimizing CDF-Funded Construction Projects in the Copperbelt Province, Zambia . Journal of Contemporary Urban Affairs, 9(1), 290–309. https://doi.org/10.25034/ijcua.2025.v9n1-15

Plaudit